The refurbishment works are progressing well with all of the building’s structural work completed. As we run up to Christmas, we will have the floors laid, first fix of the electrics and plumbing concluded, the walls insulated and prepared for plaster boarding and skimming. To get the refurbishment project to this stage has been a huge undertaking though not without the odd unexpected challenge. The main fabric of the original building is constructed from sandstone, which has been in place for hundreds of years. The mud, straw, and horsehair holding much of it together do not fare well over such […]