Progress Update 22 09 24

We have had yet another productive week with the lower rear roof timberwork being completed as well as the raising of an upstairs lintel. An internal wall in the bar area and the fireplace have been removed, increasing the size of the bar area. In the coming days the slating of the lower roof will be complete as well as the rebuilding of the wall below the bay window. The biggest change has been the completion of the painting of the front of the pub; it looks amazing! You can now view photographs of the pub before the refurbishment started […]