Share Offer Extension to June 2025

The refurbishment works are progressing well with all of the building’s structural work completed as of the end of November 2024. To get to this stage has been a huge undertaking though not without the odd unexpected challenge. The main fabric of the original building is constructed from sandstone, which has been in place for hundreds of years. The mud, straw, and horsehair holding much of it together do not fare well over such extended periods! As a result, and with regularity, every time we remove some plaster or lift a piece of timber there is another cracked wall or […]

Christmas Event 2024

You are invited to a Christmas celebration at The Golden Lion, Ashton Hayes. The event will take place on Sunday 22nd December between 12pm and 2pm and we will be serving mulled wine, Weetwood beer, hot chocolate and mince pies. Hopefully, numbers permitting, you will be able to have a quick look inside at the progress made so far with the help of our wonderful volunteers. Parking will be very limited and there are hazards on the car park so please walk if at all possible and enter the courtyard at the back of the pub via the car park. Children are welcome […]

Progress Update 25 11 24

The refurbishment works are progressing well with all of the building’s structural work completed. As we run up to Christmas, we will have the floors laid, first fix of the electrics and plumbing concluded, the walls insulated and prepared for plaster boarding and skimming. To get the refurbishment project to this stage has been a huge undertaking though not without the odd unexpected challenge. The main fabric of the original building is constructed from sandstone, which has been in place for hundreds of years. The mud, straw, and horsehair holding much of it together do not fare well over such […]

Progress Update 09 11 24

We have again made great progress with the help of our brilliant volunteers. The electric, plumbing and insulation works continue but the main change is the completion of the courtyard area and pathway.           The pathway connects the carpark to Kelsall Road near the phonebox, this provide plenty of parking and safe access to the Community Shop and Post Office. The carpark is not yet in use but we will let you know when it is safe to use the car park and pathway. On Saturday we had a small group of volunteers in to clear the […]

Progress Update 28 10 24

Ashton Hayes Community Hub Ltd. are proud to announce that we won The One to Watch Award at the Plunkett Rural Community Business Awards in London. To find out more about the award visit their website: https://plunkett.co.uk/rural-community-business-awards. While all that excitement was going on we also had a number of jobs take place at the pub. The CCTV was installed and the vaulted ceiling and joist repair works were completed. The landscaping of the pathway and beer garden began with the removal of the old brick stairs.   We also had three volunteer sessions to install external wall insulation, they […]

Progress Update 20 10 24

We had a very productive volunteer session this week, clearing space for the solar panel battery installation and prepping for installation of the plasterboards. We also had some structural work done to the beer garden and the electrician and CCTV people had their final visit before first fix begins. Also, work began on the internal flooring. The best news is, that we now have a staircase so no more climbing up the ladder! Next week the pathway groundworks begin, the CCTV is being installed and the flooring work continues. We also have two volunteer sessions planned to clear old piping, […]